What is MrP

Materials requirement planning is a software system designed in the early 20th century to improve the productivity of businesses and was one of the first systems used to create a lean manufacturing system.

Why do MRP projects fail, and how to avoid these mistakes?

  • Overkill

Many small businesses implement large systems which are too costly and complex due to their sheer size. Over-investing in an MRP system will lead to cash flow crunches, resource shortages, and inefficient implementation. Most small businesses only need a handful of solutions to solve a handful of critical problems. Therefore, it is crucial to identify the fundamental issues that require an MRP system and then decide on the key MRP modules to implement. Modular implementation of a plan gives you a safety net. It’s like dipping your pool in the water before jumping in it. 

  • Insufficient planning and assessment 

Do I need an MRP system just yet? Can I afford it? Do I have the capacity to implement an MRP system? Jumping into management fads without answering these questions often leads to hurdles and resource crunches later in the implementation process, leading to implementation failure. Therefore, it is crucial to analyze the current position to determine the solution for the company. In a dynamic business environment, the longer the implementation process, the higher the chances of failure since it becomes difficult to keep people engaged in such long-term implementation projects. 

  • Resistance to change 

People are the main obstacle to a successful MRP implementation. Your staff may view an MRP system as job killers due to their ability to automate certain aspects of the production process, leading to organization members sabotaging the project to continue business as usual and protecting their jobs. Therefore it is essential to use a classical approach to organizational change and involve as much affected personnel in the planning, designing, and implementation stage. Involvement in implementation will make them a part of the decision-making process. Educating staff and training them will help them understand how the MRP system can help them do their job more efficiently and contribute to its growth. An open channel of communications and education about the benefits of MRP will aid in the change management process. 

  • Lack of Training 

The idea of sudden implementation is often the cause of failure as it makes it difficult for the staff to adapt to the system and perform their regular duties efficiently at the same time. 

Therefore, training staff in the testing phases and providing them with the necessary skill set is imperative to successfully implementing the system since they will be using the system. 

Management often overlooks training & skill development for MRP systems in the implementation phase, resulting in inadequate and incomplete training. Since training and education also aim to change people’s behavior, lousy training will lead to non-conformance to the objective of implementation.

  • Unstructured Approach

Projects as complex as MRP implementation require proper project management. Complex projects require a project team or implementation committee to oversee the project, deadlines, cost and provide the necessary resources for successful implementation. Unstructured approaches lead to deadlines piling up, milestones getting pushed, and increasing costs for the company, which will throw off your cost to benefit ratio of implementing the system. 

  • A lazy approach to implementation

An MRP implementation is as complex as redesigning your production process with added variables to it. If the project is not taken seriously, it will fall apart quickly due to its complexity and cost. Seamless and efficient implementing an MRP system requires a dedicated effort from the whole company, including top management and floor level staff. 

How to choose the best MRP system for your company?

  1. Size of the company 

Generally, an MRP system works well for a small business and is cheaper to implement than an ERP system. It is also simpler to implement an MRP system as ERP systems are vast and complex to implement. ERP systems are made for large-scale companies that can afford to invest money and implement large complex systems. ERP systems require complex databases and heavy processing systems that are pretty costly. The best option for small businesses is to start with an MRP II system and then move on to an ERP system as they grow. 

  1. The functionality of the software

ERP systems are built on top of MRP II systems and are very expansive since they are typically made for large companies. On the other hand, MRP II systems are confined to the manufacturing process and are less generally more affordable. Therefore, if an MRP system can provide you with the solution you are looking for, small businesses should implement an MRP system and then get it customized to their needs. 

  1. Inventory Control 

One of the core functionalities of an MRP is inventory planning. The best MRP systems for small businesses are the ones that have robust inventory planning modules and give you complete control over your inventory management system. Some of the must-have features are real-time stock adjustment, tracking of products and raw materials, and the ability to automate procurement by setting Reorder points (ROP)

  1. Reporting the cost of production 

MRP systems must be able to automate the tracking of production costs through the production process. An MRP system must accurately determine the cost of production to help you make sensible and informed pricing decisions.

  1. Capacity for Production planning

Production planning is the most crucial element in creating an efficient manufacturing system. A sound MRP system comes equipped with an easy production planning system that helps you determine the resources needed to meet independent demand, including labor and machine capacity. 

  1. Seamless

It is vital to have a dashboard that helps you view all the information in an organized manner and use the system quickly. A digital strategy that is easy to use increases the likelihood that the system will successfully meet the company’s goals. 

  1. User-friendly interface

Often the success or failure of a system depends on the people who are using the system. Therefore, an MRP system must be easy to use so that it is easy to train the staff to use the system properly. 

  1. Integration

It is vital to choose a system that will interact and pull data from your legacy systems while also connecting to third-party systems that you may wish to integrate in the future. A close-ended MRP system generally makes it difficult to integrate existing or new software into your production system. Therefore, it is crucial to choose flexible  MRP software to fit in with your integration requirements. 

Elements of an MRP system

  1. Business Planning 

Business Plans are created in dollar value and grouped by product family refers to creating:

  • A long term strategy
  • Revenue, costs, and profit objectives supported by budgets
  • Projected balance sheet and cash flow statement

These plans are translated into execution plans using production planning/sales and operations planning. 

  1. Production Planning 

Production plans or sales & operation plans are tactical plans used to set the overall output of the manufacturing process to achieve the sales target best while meeting the general business objectives like profitability, customer satisfaction, and on-time delivery, etc. 

It is crucial to compare the sales to the production capabilities to formulate a viable business strategy that will include prediction plans, budgets, financials, and plans for materials and workforce requirements. The primary purpose of a production plant is to achieve a stable production rate and productive efficiency that will enable the company to satisfy overall demand by raising, maintaining, or lowering the inventory backlog while maintaining a regular supply of other resources like labor, cash, and machines. Production plans are the central hub for any manufacturing company. They hence are prepared by a team of people from marketing, manufacturing, sales, engineering, finance, inventory management, and other essential departments. 

  1. Master Production Scheduling

Master production scheduling refers to developing a master production schedule that reflects what the company plans to produce in quantity, configurations, and dates. It used creating forecasts, production plans, customer demand, production backlog, material & capacity availability, and organizational goals 

  1. Sales Forecasts

Sales forecasts are estimates of future demand constructed using quantitative, qualitative methods or a combination of both, based on internal and external factors affecting market demand. Sales forecast helps identify the four components of demand: seasonality, cyclicity, randomness, and trends.

  1. Capacity Planning 

Capacity planning is the process of determining the total capacity required to produce the goods needed to meet the entire demand successfully. The type of forecasting depends on the level it is performed at:

  • Resource requirement planning or resource planning: Refers to the process of establishing, measuring, and adjusting limits or levels of long-range capacity performed at a business plan or product-line level. It is usually based on the production plan and used to create the bill of resources that help plan for resources that take a long time to acquire. 
  • Rough Cut capacity planning: It is performed at a master scheduling level and used to convert the master production schedule into the requirement for critical resources like machinery, labor, warehouse space, suppliers, and money. 
  1. Production Scheduling

Production scheduling is the process of developing a production schedule using the production plan. Scheduling helps to efficiently execute the production plan depending on delivery dates, urgency, resource availability, and other factors. It defines every production run, the quantity, and the timing of production. 

  1. Bill of Materials (BOM)

The bill of materials is created from the finished goods schedule data provided by the MPS. It contains a listing and quantity of all the sub-assemblies, parts,  intermediates, and raw materials used to produce the items listed on the MPS. In addition, it helps to determine things for which production orders or purchase requisitions need to be released. BOM can be an indented, single-level, modular, transient, matrix, or costed BOM. It is also called formula, recipe, or ingredient list in specific industries depending on the product. 

  1. Materials Requirement Planning 

Material Requirements Planning is responsible for resource allocation and job release functions. It releases material onto the shop floor and converts them into scheduled receipts. The output of materials requirement planning is the job pool, which consists of planned order releases.

  1. Capacity requirement planning

CRP  helps to match the MPS to the available resources in the production process. It helps determine the quantity and nature of labor, production machinery, operation management unit, and other resources required to meet the production objectives of the MPS and Materials requirement planning. It uses shop orders from the MRP system to track part routings and time standards to determine work hours by work center. Sometimes RCCP and CRP may differ due to the addition of time as a variable when determining the availability of resources at this level. 

It also helps the company understand how much it needs to produce and whether or not it can meet those production goals given the available resources. Therefore, small businesses must conduct CRP regularly to cope with changes in supply and demand. 

CRP Inputs:

  • Planned orders and release orders from the MRP system 
  • Loading information from the work center status file 
  • Routing information from the shop routing file 
  • Modify capacity and provide alternative routings or planned orders. 

CRP Outputs:

  • Rescheduling information that requires capacity modification
  • Revision of the Master Production Schedule (MPS) 
  • Verification of planned orders for the MRP system 
  • Load reports Keeping in view the above discussion; the following diagram provides the underlying logic of Capacity Requirements Planning (CRP).

Planning Stages of an MRP system

Step 1: General Long-Term Planning 

Long-term planning ranges from 6 months to five years, including a monthly or weekly replanning. It is based on the product mix and performed at a corporate level as it affects all the manufacturing facilities owned by the firm. Forecasting helps to determine future demand, capacity requirement, machinery, and personnel. Resource planning is used to determine the capacity requirements over the long term to make decisions about expansion plans. Finally, aggregate planning determines production level, staffing, and inventor requirements over a long time based on the planning period and product mix. 

Step 2: Detailed Intermediate Planning

Intermediate planning is performed by the production management team at the plant level and helps define the different functions during production. This stage involves Master production scheduling (MPS), Materials requirement planning, Bill of resources, rough-cut Capacity Planning, and capacity requirement planning. Demand management refers to converting the long-term demand forecasts into a detailed forecast, tracking individual customer orders. MPS is the source of demand in an MRP system as it provides the system with information about quantities and due dates of the independent demand of orders. Finally, rough-cut capacity planning runs a quick check on all the available resources to determine the feasibility of the MPS. 

Short Term Planning 

Short-term planning is used to manage released work orders and purchase orders while executing the production schedule. It ensures the timely completion of a work order in the correct quantity and specifications. Purchase orders are meant for external manufacturers or outsourced processes, whereas Shop floor control is for internal manufacturing processes. The function of short-term planning is to ensure efficient job dispatching while maintaining input and output controls. 

Job Dispatching refers to the rules for queuing jobs at a workstation on the production floor to maintain data integrity, reduce delays and lead time, maximize machine utilization, and maximize throughput of a process. Some examples of job dispatching rules are Shortest Process time, Least Slack, critical ratio. 

Input/Output control checks release against available capacity at any given time. Shop floor control systems compare actual WIP levels to pre-determined WIP. Depending on the WIP level, SFC can alter the release rate of work orders by adjusting the MPS until the process can achieve the correct rate, given the state of the production process. 

 

How does MRP II work?

Stage 1: Production & Demand Planning 

MRP II systems synchronize all aspects of the business. The system helps coordinate sales, purchasing, manufacturing, finance, and engineering by adopting a focal production plan and using a unified and centralized database to plan and update all systems’ activities. 

The process starts with creating a production plan that will specify the monthly production level for every product line for the next one to five years. It is made using the business plan, marketing plan, sales forecast, demand forecasts, and customer demand. Since a production plan affects all functional departments in a manufacturing company, it must be developed in coordination with all important departments like strategy, marketing, sales, finance, HR, Inventory management, production planning. Production will ensure it meets the production levels, and sales will be expected to sell at the production level so that the company can reduce the holding cost of finished goods and improve finished goods inventory turnover. Finance must ensure adequate resources are available to achieve these goals.

Master production scheduling is a process that converts the production plan into a master production schedule. MPS uses information from production strategy diversifications and sales, budget, stock level, forecasts, customer orders, and sales orders to create the finished goods schedule and the weekly quantities of each product line to be manufactured. 

RRP systems cross-check the resource availability to determine if adequate resources are available to meet the independent demand. If resources are unavailable, the system reverts to the business planning and MPS stage to readjust the MPS to fit resource availability. In case the resources are available, the MPS then moves to the materials planning stage. 

Stage 2: Materials Requirement planning & Capacity Requirement planning 

Materials requirement planning pulls information from the bill of materials, stock, work in progress, handling rules, and lead times to determine the total material required to fulfill the independent demand. It then compares the gross requirement against the in-stock level, gives out the net requirement. If there is a shortage, the system automatically creates purchase orders to procure the necessary material and places an order based on calculated lead time to ensure the availability of materials when needed. 

Capacity requirement planning uses planned order releases, existing WIP positions, routing data, and capacity and lead time for work centers to provide a more detailed insight in the capacity check than rough-cut capacity planning. It performs infinite forward loading to predict loading over time using the expected job completion time for each process given the fixed lead time. It corrects over and underloading by comparing loading values against the available capacity.  

Stage 3: Production Scheduling

Once material planning has been completed, the next step is to create a production schedule. Scheduling is a more in-depth version of production planning. First, the system will determine the optimal production runs based on resource availability, lead times, delivery dates, and throughput. Next, the system calculates the workloads by using the schedule, routing, workstation, capacity, and efficiency-related information. At this stage, the system again cross-checks for available resources. If there aren’t sufficient resources to execute the production schedule, the system goes back to the production planning stage to create a more efficient and achievable production plan. 

Stage 4: Production Execution & Control 

Suppose there are enough resources to execute the production schedule. In that case, the system will create a loading schedule that determines the release rate of work orders depending on available capacity at each workstation. 

Work orders and purchase orders are created based on the manufacturing schedule. Resources are then allocated to each job using a resource allocation system. The resource allocation system ensures sufficient resources are available for each job to be executed efficiently. 

The system then monitors the production process to account for materials consumed, rejects, defects, final output, and other production-related information using the production tracking system. 

SFC is responsible for controlling job dispatch and input/output controls. It determines the job dispatching rules and reconfigures the queuing rate. Shop floor control systems also help determine the WIP status and readjust the MPS work orders depending on available capacity at each workstation to achieve the optimum work order release rate. 

Next, the system measures the performance of the production process using metrics such as throughput, lead time, and yield and creates reports based on these metrics to improve production planning and execution. This performance data is then sent to the production planning stage to provide feedback about the quality of production planning. The feedback system keeps all relevant departments informed about operations progress, enabling them to adjust agreeably to changes in the production of the plan. Thus, careless vendor delivery, machine breakdowns, or customer requests for a quicker delivery of an order will be fed back into the requirements planning system to modify all the schedules for related sub-components.